48.
What does the critical path in PERT represent ?
1. The shortest path for the earliest completion of the project.
2. The longest path of the network from the initial to final event,
1. The shortest path for the earliest completion of the project.
2. The longest path of the network from the initial to final event,
Discussion:
1 comments Page 1 of 1.
Umesh H A said:
7 years ago
Pert is Event oriented.
The probabilistic model used during the rocket launch by USA, to predict the probabilistic time of an event.
The probabilistic model used during the rocket launch by USA, to predict the probabilistic time of an event.