Civil Engineering - UPSC Civil Service Exam Questions - Discussion

Discussion Forum : UPSC Civil Service Exam Questions - Section 13 (Q.No. 48)
48.
What does the critical path in PERT represent ?
1. The shortest path for the earliest completion of the project.
2. The longest path of the network from the initial to final event,
1 only
2 only
Both 1 and 2
Neither 1 nor 2
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Umesh H A said:   7 years ago
Pert is Event oriented.

The probabilistic model used during the rocket launch by USA, to predict the probabilistic time of an event.