Discussion Forum : UPSC Civil Service Exam Questions - Section 25 (Q.No. 40)
40.
The following steps are involved in arriving at a unit hydrograph.
1. Estimating the surface runoff in depth.
2. Estimating the surface runoff in volume.
3. Separation of base flow.
4. Dividing surface runoff ordinates by depth of runoff.
The correct sequence of the steps is :
1. Estimating the surface runoff in depth.
2. Estimating the surface runoff in volume.
3. Separation of base flow.
4. Dividing surface runoff ordinates by depth of runoff.
The correct sequence of the steps is :
Discussion:
5 comments Page 1 of 1.
Arsh said:
9 years ago
I think A is correct.
Reena said:
7 years ago
Yes, A is correct.
Bhutan said:
6 years ago
A is the correct answer.
H.A said:
4 years ago
I think A is the correct answer.
Rahul said:
2 years ago
I think A is correct.