Civil Engineering - UPSC Civil Service Exam Questions - Discussion
Discussion Forum : UPSC Civil Service Exam Questions - Section 25 (Q.No. 40)
40.
The following steps are involved in arriving at a unit hydrograph.
1. Estimating the surface runoff in depth.
2. Estimating the surface runoff in volume.
3. Separation of base flow.
4. Dividing surface runoff ordinates by depth of runoff.
The correct sequence of the steps is :
1. Estimating the surface runoff in depth.
2. Estimating the surface runoff in volume.
3. Separation of base flow.
4. Dividing surface runoff ordinates by depth of runoff.
The correct sequence of the steps is :
Discussion:
5 comments Page 1 of 1.
Rahul said:
2 years ago
I think A is correct.
H.A said:
4 years ago
I think A is the correct answer.
Bhutan said:
6 years ago
A is the correct answer.
Reena said:
7 years ago
Yes, A is correct.
Arsh said:
9 years ago
I think A is correct.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers