Civil Engineering - UPSC Civil Service Exam Questions - Discussion
Discussion Forum : UPSC Civil Service Exam Questions - Section 1 (Q.No. 2)
2.
The following steps are involved in laying a sewer in a trench :
1. Transferring the center line of the sewer to the bottom trench.
2. Setting sight rails over the trench.
3. Driving pegs to the level of the invert line of the sewer.
4. Placing the sewer of these steps is The correct sequence of these steps is
1. Transferring the center line of the sewer to the bottom trench.
2. Setting sight rails over the trench.
3. Driving pegs to the level of the invert line of the sewer.
4. Placing the sewer of these steps is The correct sequence of these steps is
Discussion:
4 comments Page 1 of 1.
RAJA said:
4 years ago
The correct order is;
1. Setting,
2. Driving,
3. Transferring, &
4. Laying or Placing.
1. Setting,
2. Driving,
3. Transferring, &
4. Laying or Placing.
(1)
Kris said:
3 years ago
The correct oder is;
1. Settings.
2. Driving.
3. Transferring.
4. Laying or placing.
1. Settings.
2. Driving.
3. Transferring.
4. Laying or placing.
(2)
Aniket said:
1 decade ago
1. Setting,
2. Driving,
3. Transferring, &
4. Laying or Placing.
2. Driving,
3. Transferring, &
4. Laying or Placing.
(1)
Anand Kumar said:
8 years ago
1. Setting.
2. Driving.
3. Transforming.
4. Laying or placing.
2. Driving.
3. Transforming.
4. Laying or placing.
(1)