The following steps are involved in laying a sewer in a trench :
1. Transferring the center line of the sewer to the bottom trench.
2. Setting sight rails over the trench.
3. Driving pegs to the level of the invert line of the sewer.
4. Placing the sewer of these steps is The correct sequence of these steps is
1, 2, 3, 4
2, 3, 4, 1
4, 2, 3, 1
2, 3, 1, 4
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Aniket said:   1 decade ago
1. Setting,
2. Driving,
3. Transferring, &
4. Laying or Placing.
(1)

Anand Kumar said:   8 years ago
1. Setting.
2. Driving.
3. Transforming.
4. Laying or placing.
(1)

RAJA said:   4 years ago
The correct order is;

1. Setting,
2. Driving,
3. Transferring, &
4. Laying or Placing.
(1)

Kris said:   3 years ago
The correct oder is;

1. Settings.
2. Driving.
3. Transferring.
4. Laying or placing.
(2)