33.
For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is
8
7
9
11
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
8 comments Page 1 of 1.

Rahul verma said:   3 years ago
Option C is the correct answer. Please explain me.

Rakeah said:   9 years ago
According to me, option c is correct answer.

Phani said:   7 years ago
According to me, 7 is the correct answer.

Shaharukh said:   7 years ago
According to me, 7 is correct answer.

Gaurvendra said:   7 years ago
The Correct option is C not A.

Pops said:   8 years ago
1+1+5=7 answer should be B.

Chhhaya said:   8 years ago
Yes, option C is correct.

Priyanka said:   5 years ago
C is correct