Civil Engineering - UPSC Civil Service Exam Questions - Discussion
Discussion Forum : UPSC Civil Service Exam Questions - Section 12 (Q.No. 33)
33.
For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is


Discussion:
8 comments Page 1 of 1.
Rahul verma said:
3 years ago
Option C is the correct answer. Please explain me.
Priyanka said:
5 years ago
C is correct
Shaharukh said:
7 years ago
According to me, 7 is correct answer.
Gaurvendra said:
7 years ago
The Correct option is C not A.
Phani said:
7 years ago
According to me, 7 is the correct answer.
Pops said:
8 years ago
1+1+5=7 answer should be B.
Chhhaya said:
8 years ago
Yes, option C is correct.
Rakeah said:
9 years ago
According to me, option c is correct answer.