Civil Engineering - UPSC Civil Service Exam Questions - Discussion

Discussion Forum : UPSC Civil Service Exam Questions - Section 12 (Q.No. 33)
33.
For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is
8
7
9
11
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
8 comments Page 1 of 1.

Rahul verma said:   3 years ago
Option C is the correct answer. Please explain me.

Priyanka said:   5 years ago
C is correct

Shaharukh said:   7 years ago
According to me, 7 is correct answer.

Gaurvendra said:   7 years ago
The Correct option is C not A.

Phani said:   7 years ago
According to me, 7 is the correct answer.

Pops said:   8 years ago
1+1+5=7 answer should be B.

Chhhaya said:   8 years ago
Yes, option C is correct.

Rakeah said:   9 years ago
According to me, option c is correct answer.

Post your comments here:

Your comments will be displayed after verification.