Civil Engineering - UPSC Civil Service Exam Questions
Exercise : UPSC Civil Service Exam Questions - Section 14
- UPSC Civil Service Exam Questions - Section 14
- UPSC Civil Service Exam Questions - Section 27
- UPSC Civil Service Exam Questions - Section 26
- UPSC Civil Service Exam Questions - Section 25
- UPSC Civil Service Exam Questions - Section 24
- UPSC Civil Service Exam Questions - Section 23
- UPSC Civil Service Exam Questions - Section 22
- UPSC Civil Service Exam Questions - Section 21
- UPSC Civil Service Exam Questions - Section 20
- UPSC Civil Service Exam Questions - Section 19
- UPSC Civil Service Exam Questions - Section 18
- UPSC Civil Service Exam Questions - Section 17
- UPSC Civil Service Exam Questions - Section 16
- UPSC Civil Service Exam Questions - Section 15
- UPSC Civil Service Exam Questions - Section 1
- UPSC Civil Service Exam Questions - Section 13
- UPSC Civil Service Exam Questions - Section 12
- UPSC Civil Service Exam Questions - Section 11
- UPSC Civil Service Exam Questions - Section 10
- UPSC Civil Service Exam Questions - Section 9
- UPSC Civil Service Exam Questions - Section 8
- UPSC Civil Service Exam Questions - Section 7
- UPSC Civil Service Exam Questions - Section 6
- UPSC Civil Service Exam Questions - Section 5
- UPSC Civil Service Exam Questions - Section 4
- UPSC Civil Service Exam Questions - Section 3
- UPSC Civil Service Exam Questions - Section 2
11.
Which of the following measures are resorted to for strengthening masonry walls ?
1. Provide cross walls.
2. Pre-stressing.
3. Provide gunite slab on the surface(s) of walls.
4. Provide buttresses.
Select the correct answer using the code given below :
1. Provide cross walls.
2. Pre-stressing.
3. Provide gunite slab on the surface(s) of walls.
4. Provide buttresses.
Select the correct answer using the code given below :
12.
Which one of the following surveys is employed for collecting sufficient data in connection with sewage disposal and water supply works ?
13.
Cost-benefit studies are essential to
14.
What is the value of flexural strength of M 25 concrete ?
15.
The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remolded sampler is