The following operations are required for tunnelling in rocky terrain :
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :