In case of reduction of levels by the height of instrument method,
Discussion:
22 comments Page 2 of 3.
Raihan KAIZEN said:
7 years ago
Yes, absolutely option D is the correct option. I agree.
Zeshan Akram said:
7 years ago
You are Right, thanks @PAVAN.
Abhik said:
6 years ago
Only option A is correct.
Pankaj jha said:
6 years ago
B.S. - F.S. = difference in R.L.S of the first station and last station is correct.
C.KARTHIKEYAN said:
6 years ago
A is the correct answer.
Arjun m said:
6 years ago
When we are writing as equation format first-last and last- first matters.
But mentioning as the difference of Last RL and First RL /Last RL and First RL is same.
But mentioning as the difference of Last RL and First RL /Last RL and First RL is same.
(1)
ManiSivan said:
6 years ago
Arithmetic check :
Sum of BS - Sum of FS = Last RL - First RL
Sum of BS - Sum of FS = Last RL - First RL
Hruaia said:
5 years ago
According to me, A is correct.
Dhan Bahadur bist said:
4 years ago
Height of instruments method is;
= Sum Bs - sum fs= last Rl - first Rl.
= Sum Bs - sum fs= last Rl - first Rl.
(1)
Uttam said:
3 years ago
Thank you all for explaining the answer.