Civil Engineering - Surveying - Discussion
Discussion Forum : Surveying - Section 3 (Q.No. 16)
16.
In case of reduction of levels by the height of instrument method,
Discussion:
21 comments Page 1 of 3.
Deva said:
3 months ago
According to me, A is the right answer.
Uttam said:
5 months ago
Thank you all for explaining the answer.
Dhan Bahadur bist said:
1 year ago
Height of instruments method is;
= Sum Bs - sum fs= last Rl - first Rl.
= Sum Bs - sum fs= last Rl - first Rl.
Hruaia said:
3 years ago
According to me, A is correct.
ManiSivan said:
3 years ago
Arithmetic check :
Sum of BS - Sum of FS = Last RL - First RL
Sum of BS - Sum of FS = Last RL - First RL
Arjun m said:
4 years ago
When we are writing as equation format first-last and last- first matters.
But mentioning as the difference of Last RL and First RL /Last RL and First RL is same.
But mentioning as the difference of Last RL and First RL /Last RL and First RL is same.
C.KARTHIKEYAN said:
4 years ago
A is the correct answer.
Pankaj jha said:
4 years ago
B.S. - F.S. = difference in R.L.S of the first station and last station is correct.
Abhik said:
4 years ago
Only option A is correct.
Zeshan Akram said:
4 years ago
You are Right, thanks @PAVAN.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers