Discussion Forum : Surveying - Section 5 (Q.No. 36)
36.
Number of subdivisions per metre length of a levelling staff is
100
200
500
1000
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
7 comments Page 1 of 1.

Raja Reddy said:   9 years ago
Each sub division = 5mm,
1m = 1000mm,
1000/5 = 200.
(2)

Fahad said:   7 years ago
Thanks @Raja.

Amu bokato said:   6 years ago
Thanks a lot @Raja Reddy.

Manju said:   6 years ago
How 5mm? Please tell me.
(2)

Jinish said:   6 years ago
The distance of 1 between to redline in leveling staff is 5 mm so subdivision is 5 mm.

For 1 meter length- 1000/5 so answer is 200 mm.

R.k said:   6 years ago
Thanks @Raja reddy.

JEET said:   6 years ago
Here Each sub division = 5mm,
1m = 1000mm,
So, 1000/5 = 200.
(8)