Civil Engineering - Surveying - Discussion
Discussion Forum : Surveying - Section 6 (Q.No. 45)
45.
In setting up a plane table at any station
Discussion:
20 comments Page 2 of 2.
Kamil ali said:
6 years ago
Levelling is done first.
Mayur salvi said:
6 years ago
Setting up a plane table the operation which is done first is levelling.
Shubham said:
6 years ago
(1). leveling the table.
(2). Orienting the table.
(3). Centering the table.
(2). Orienting the table.
(3). Centering the table.
ErN said:
5 years ago
For the Plane table:
1. Levelling
2. Centering
3. Orientation
For Prismatic compass:
1. Centering
2. Levelling
3. Focusing the Prism.
1. Levelling
2. Centering
3. Orientation
For Prismatic compass:
1. Centering
2. Levelling
3. Focusing the Prism.
(7)
Sandeep sahu said:
5 years ago
The order is Levelling, centering, orientation.
(2)
Biraj Thapa said:
5 years ago
What is the correct order of procedure of levelling of plane table surveying?
MJM Gcek said:
4 years ago
It should be, Levelling is done first.
(2)
Jiban rout said:
4 years ago
If you move the tripod stand circumferential then centring position don't change but levelling affected.
If tripod legs moves radially then it don't affect the levelling but centring does.
If tripod legs moves radially then it don't affect the levelling but centring does.
(1)
Beekram Lama said:
3 years ago
In the plane table;
1. Levelling
2. Centering
3. Orientation
Levelling is done first and centring and orientation may be done simultaneously as the orientation disturbs centring and vice-versa
1. Levelling
2. Centering
3. Orientation
Levelling is done first and centring and orientation may be done simultaneously as the orientation disturbs centring and vice-versa
(4)
Farzana kouser said:
3 years ago
The correct order is;.
1. Centering.
2. Levelling.
3. Orientation.
1. Centering.
2. Levelling.
3. Orientation.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers