Civil Engineering - Surveying - Discussion
Discussion Forum : Surveying - Section 6 (Q.No. 45)
45.
In setting up a plane table at any station
Discussion:
20 comments Page 1 of 2.
Farzana kouser said:
3 years ago
The correct order is;.
1. Centering.
2. Levelling.
3. Orientation.
1. Centering.
2. Levelling.
3. Orientation.
Beekram Lama said:
3 years ago
In the plane table;
1. Levelling
2. Centering
3. Orientation
Levelling is done first and centring and orientation may be done simultaneously as the orientation disturbs centring and vice-versa
1. Levelling
2. Centering
3. Orientation
Levelling is done first and centring and orientation may be done simultaneously as the orientation disturbs centring and vice-versa
(4)
Jiban rout said:
4 years ago
If you move the tripod stand circumferential then centring position don't change but levelling affected.
If tripod legs moves radially then it don't affect the levelling but centring does.
If tripod legs moves radially then it don't affect the levelling but centring does.
(1)
MJM Gcek said:
4 years ago
It should be, Levelling is done first.
(2)
Biraj Thapa said:
5 years ago
What is the correct order of procedure of levelling of plane table surveying?
Sandeep sahu said:
5 years ago
The order is Levelling, centering, orientation.
(2)
ErN said:
5 years ago
For the Plane table:
1. Levelling
2. Centering
3. Orientation
For Prismatic compass:
1. Centering
2. Levelling
3. Focusing the Prism.
1. Levelling
2. Centering
3. Orientation
For Prismatic compass:
1. Centering
2. Levelling
3. Focusing the Prism.
(7)
Shubham said:
5 years ago
(1). leveling the table.
(2). Orienting the table.
(3). Centering the table.
(2). Orienting the table.
(3). Centering the table.
Mayur salvi said:
6 years ago
Setting up a plane table the operation which is done first is levelling.
Kamil ali said:
6 years ago
Levelling is done first.
Post your comments here: