29.
If a 0.7% upgrade meets a 0.65% downgrade at a summit and the permissible rate of change of grade per chain length is 0.10%, the length of the vertical curve, is
Discussion:
4 comments Page 1 of 1.
Akash said:
7 years ago
@Ranjan.
It will be 13.5.
It will be 13.5.
(1)
Murali said:
8 years ago
Thanks @Ranjan.
(1)
RANJAN PATRA said:
9 years ago
@Syam Babu.
.7 + .65/ .1 = 13.5 = 14 CHAINs.
.7 + .65/ .1 = 13.5 = 14 CHAINs.
(1)
SYAM babu s said:
10 years ago
How getting this answer? Please any one give explanations to it.