6. 

The difference in level between the top of a bank and supply level in a canal, is called

A. berm
B. free board
C. height of bank
D. none of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

7. 

F.S.L. of a canal at its head with respect to parent channel is kept

A. at the same level
B. 15 cm lower
C. 15 cm higher
D. none of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

8. 

The measure to remove water logging of land, is

A. to reduce percolation from canals and water courses
B. to increase outflow from the ground water reservoir
C. both (a) and (b)
D. neither (a) nor (b)

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

9. 

Attracting groynes are built

A. perpendicular to the bank
B. inclined down stream
C. inclined up stream
D. none of these.

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

10. 

Retrogression of the bed level of a river downstream a weir, occurs due to

A. heavy impact of water
B. increase of the bed level
C. less percentage of silt
D. soft soil strata.

Answer: Option C

Explanation: