34.
At a road junction, 16 cross conflict points are severe, if
both are one-way roads
both are two-way roads
one is two-way road and other is one-way road
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
10 comments Page 1 of 1.

Raghv said:   9 years ago
It should be 24 for both two-way road.

11 for one is two-way and other one way.

& 6 for both one-way road.

Debanga Bhusan Dutta said:   8 years ago
Cross conflict points. Not all, That's why 16.
(1)

Sourish said:   8 years ago
It should be 24.

Abhi said:   7 years ago
Total Conflict Points in 2 way 2 lane highway is 24,
Cross Conflict points are 16,
Merging Conflicts are 8,
That's why 16+8=24.

S. R Jat said:   7 years ago
Total Conflict Points in 2 way 2 lane highway is 32,
Major potential Conflict points are 16,
Merging potential Conflicts are 8,
total potential conflict points16+8=24.

Pedestrian conflicts are 8.
Total Conflict Points in 2 way 2 lane highway is 24,
Cross Conflict points are 16,
Merging Conflicts are 8,
That's why total conflict points are 24+8=32.
(1)

Jasmine said:   7 years ago
Thanks for explaining @S.R Jat and @Abhi.

Pawan said:   6 years ago
Thanks @S.R Jat and @Abhi.

Vikash sharma said:   6 years ago
Sir, number of potential conflicts in 2 lane 2 way intersection?

Gurjant Singh said:   4 years ago
Conflict point for 2 lanes 1-way traffic is 6.

Conflict point for 2 lanes 2-way traffic is 24.
(1)

Wise Guru said:   3 years ago
Conflict Points for two roads of 2 lane 2 way crossing each other:.

16 crossing.
8 merging.
8 diverging.
Total: 16 + 8 + 8 = 32.