14. 

The parameters in Horton's infiltration equation are given as, fo = 7.62 cm/hour, fc = 1.34 cm/hour and k = 4.182/hour. For assumed continuous ponding the cumulative infiltration at the end of 2 hours is

[A]. 2.68 cm
[B]. 1.50 cm
[C]. 1.34 cm
[D]. 4.18 cm

Answer: Option C

Explanation:

No answer description available for this question.

Darshan said: (Aug 9, 2018)  
According to me, It should be 3.14.