Discussion Forum : GATE Exam Questions - Section 5 (Q.No. 27)
27.
Delta (Δ) in cm. Duty (D) in hectare Cumec and Base period (B) in days are related as
Discussion:
9 comments Page 1 of 1.
Yasir gandalur said:
2 years ago
A is the correct option according to the given statement.
While in the case of metre; D is the correct option.
While in the case of metre; D is the correct option.
Baloch said:
9 years ago
D is right,
Δ = 8.64 B/D (replacing delta with B) = 8.64 B/Δ.
Δ = 8.64 B/D (replacing delta with B) = 8.64 B/Δ.
Prashant rau said:
7 years ago
A is the correct answer because delta in cm.
Suman sarkar said:
8 years ago
δ= 864 B/D cm.
δ = 8.64 B/D m.
δ = 8.64 B/D m.
Rohit chandel said:
9 years ago
Yes@Rajat.
A option is the right answer.
A option is the right answer.
Nila said:
4 years ago
A is the correct option as delta in cm.
Rajat said:
1 decade ago
A option is correct as delta is in cm.
Sanath said:
8 years ago
A is the correct option.
Sunil T S said:
6 years ago
Option A is correct(cm).