Civil Engineering - GATE Exam Questions - Discussion

Discussion Forum : GATE Exam Questions - Section 1 (Q.No. 6)
6.
The wall shown in the below figure has failed. The cause of failure or the error made in the design of the failded wall is :
deep slip surface failure
overturning
no proper drainage in the clay backfill
translational failure
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
33 comments Page 2 of 4.

Pavan Kumar said:   9 years ago
Overturning causes only when the Heel position get settled right? I think it is improper drainage.

BHIMANAGOUD said:   7 years ago
Because of improper size the wall will get slide or overturned. So answer is over turning.

Girija said:   1 decade ago
The retaining wall caused by the soil pressure overcomes the overturning was had failed.
(1)

Vinay singh said:   8 years ago
We can not decide the overturning moment here so it should be improper drainage.

Sindhu said:   1 decade ago
Justify the the correct option because I feel it is due to improper drainage.

Uday kumar said:   7 years ago
Retaining wall failed in overturning & sliding. So, the answer is B.

Firdous said:   10 years ago
Overturning M due ep is more than M due to weight use pillai and menon.

Madhu said:   5 years ago
Due to overturning wall and soil pressure, the structure becomes fail.

PANKAJ PATERIYA said:   9 years ago
Because height and width ratio is not proper so fail due to O.T.

Pawan said:   3 years ago
If not clay it will be due to over turning. So the answer is C.