Civil Engineering - GATE Exam Questions - Discussion

Discussion Forum : GATE Exam Questions - Section 1 (Q.No. 6)
6.
The wall shown in the below figure has failed. The cause of failure or the error made in the design of the failded wall is :
deep slip surface failure
overturning
no proper drainage in the clay backfill
translational failure
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
33 comments Page 2 of 4.

Vinay singh said:   8 years ago
We can not decide the overturning moment here so it should be improper drainage.

Arun said:   8 years ago
Imbalance of the i.e weak in bearing capacity do cause overturning, backfill should be given precisely so as to be effective.

Anup said:   9 years ago
Because backfill donot have wide rest (heal).

Danish khan said:   9 years ago
In rainy season the water comes through weep cracks due to this the whole pressure comes on the wall.

Ankitaray said:   9 years ago
How to overturn? please explain it.

Pavan Kumar said:   9 years ago
Overturning causes only when the Heel position get settled right? I think it is improper drainage.

PANKAJ PATERIYA said:   9 years ago
Because height and width ratio is not proper so fail due to O.T.

Chinni said:   10 years ago
How overturning causes?

Firdous said:   10 years ago
Overturning M due ep is more than M due to weight use pillai and menon.

Shilpa said:   10 years ago
Here proper drainage because weep hole is here.