Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 1 (Q.No. 17)
17.
The concrete work for the following part of the building of specified thickness is measured in square metres
Discussion:
11 comments Page 1 of 2.
Aarti Nepal said:
9 years ago
In question, thickness is specified so answer is correct, all are measured in sqm in case of thickness specified.
Javed said:
9 years ago
@Gazi Dilshad.
D.P.C mean DAMP PROOF COURSE.
D.P.C mean DAMP PROOF COURSE.
Prabhat said:
9 years ago
@Avinash.
Root slab mean lintel.
Root slab mean lintel.
Aaryan malhotra said:
9 years ago
But lintel is calculated in cu.m.
Bapai baishya said:
9 years ago
The correct answer is only DPC.
Burhan Ali said:
7 years ago
E is the right answer. I agree.
Ashir said:
4 years ago
Dpc is the only correct answer.
(1)
Gazi dilshad said:
9 years ago
What the meaning of D.P.C?
Avinash said:
1 decade ago
What is root slab?
Nilutpal said:
9 years ago
Thanks @Prabhat.