The concrete work for the following part of the building of specified thickness is measured in square metres
Root slabs
Floors
D.P.C.
Wall panels
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
11 comments Page 1 of 2.

Ashir said:   4 years ago
Dpc is the only correct answer.
(1)

Burhan Ali said:   7 years ago
E is the right answer. I agree.

Aarti Nepal said:   9 years ago
In question, thickness is specified so answer is correct, all are measured in sqm in case of thickness specified.

Bapai baishya said:   9 years ago
The correct answer is only DPC.

Aaryan malhotra said:   9 years ago
But lintel is calculated in cu.m.

Nan said:   9 years ago
How roof slab?

Javed said:   9 years ago
@Gazi Dilshad.

D.P.C mean DAMP PROOF COURSE.

Gazi dilshad said:   9 years ago
What the meaning of D.P.C?

Nilutpal said:   9 years ago
Thanks @Prabhat.

Prabhat said:   9 years ago
@Avinash.

Root slab mean lintel.