Civil Engineering - Estimating and Costing - Discussion
Discussion Forum : Estimating and Costing - Section 2 (Q.No. 26)
26.
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
Discussion:
5 comments Page 1 of 1.
Yuvraj Kapgate said:
5 years ago
When sanctioned estimate is likely to exceed by more than 5% either from the rates being found insufficient or from any cause whatsoever except important structural alterations.
Anup mallik said:
8 years ago
When a sanctioned estimate is likely to exceed more than 5% due to any cause except important structural alterations.
Rahul said:
5 years ago
I think the Correct answer is 10 percent.
(1)
Shuvam said:
6 years ago
I think option B is correct answer.
Eng saeed said:
4 years ago
5% is the correct answer.