Pick up the correct statement from the following:
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurence time
Maximum value of earliest expected time is used if there are more than one value of any event
Minimum value of latest occurrence time is used if there are more than one value of any event
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.