Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 8)
8.
Pick up the PERT event from the following:
Digging of foundation started
Digging of foundation completed
Laying of concrete started
Laying of concrete completed
All the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
7 comments Page 1 of 1.

Hesham bendary said:   1 decade ago
What was the meaning of PERT?

VENUGOPAL said:   1 decade ago
Project Evaluation Review Technic.

Deepak prakash said:   10 years ago
In pert the activity is scheduled in such a way that the three time frame are taken into consideration. And they are optimistic time, pessimistic time and most likely time and related as (t0+4tm+tp)/6. To provide the most effective time for completion of the activity.

Adebola Bayewun said:   9 years ago
The alternative answers are tasks involved in the completion of a project & PERT (Programme, Evaluation, Review& Techniques is a statistical tool for analyzing the tasks so as to save time. PERT is used in controlling tasks by considering a three-time frames the optimum, pessimistic & most likely times.

Har said:   8 years ago
PERT=The program (or project) evaluation and review technique.

Makar said:   7 years ago
PERT means program evaluation revised time. Best eg is any scientific project like ISRO. Which required some time for this project but approximately.

Sag said:   9 months ago
PERT is used for an event.

Here, the start and completion of the activity are both events. So, the answer is all of the above.