Pick up the incorrect statement from the following:
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Each activity consumes a given time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Ajay said:   8 years ago
I think the dummy activity does not require any time.
(1)

Pranay Warghat said:   4 years ago
A is the correct answer.