Discussion Forum : Construction Management - Section 1 (Q.No. 2)
2.
Pick up the incorrect statement from the following:
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Each activity consumes a given time.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 1 of 2.

Sanjeev said:   1 decade ago
Arrow represents the duration of activity not scale distance between events.

Mohit said:   1 decade ago
I think option A is also correct because in a network activity is denoted by an arrow.

Ajay said:   8 years ago
I think the dummy activity does not require any time.
(1)

Rajarshi said:   8 years ago
Dummy activity doesn't any resource or time for completion. So the correct answer will be D & E.
(1)

Muluken said:   8 years ago
Option 'E' can be an answer. Because dummy activity is an activity but which do not require any time frame or the duration is zero unit of time.

Debashis said:   8 years ago
Option E is the answer as dummy activity doesn't consume any time.
(1)

Umar Bin Abdul Aziz said:   7 years ago
A bigger arrow would represent activity with larger duration, same goes for the smaller arrow, so how come D is correct?
(1)

Gajendra Raj Joshi said:   6 years ago
@All.

Arrow doesn't represent the amount of duration. We don't treat it the way we treat vectors. It is the basic rule of network diagram.

Gaurav kumar said:   4 years ago
There is no significance of the length of the arrow in the project network.

It can be drawn from left to right or right to left.
(2)

Pranay Warghat said:   4 years ago
A is the correct answer.