Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 5 (Q.No. 29)
29.
For a concrete mix 1:3:6 and water cement ratio 0.6 both by weight, the quantity of water required per bag, is
Discussion:
57 comments Page 4 of 6.
Nilesh said:
8 years ago
W/c ratio means the ratio of the weight of water to the weight of cement so that 0.6 * 50 = 30 kits or kg.
Ar. SALMAN AFAQUE said:
9 years ago
1:3:6, so we multiply by 1*50 Kg cement and 3 fine aggregate * 50 kg, so.
We get 150 kg fine aggregate.
We get 150 kg fine aggregate.
ARNAB ADAK said:
9 years ago
For ratio, 1:3:6 w/c ratio-0.60.
So water required for 1 bag (50 kg) cement is=50*0.60=30 lit.
So water required for 1 bag (50 kg) cement is=50*0.60=30 lit.
Shubham Angre said:
4 years ago
28% of water is required for the concrete mix and 1 bag of cement = 50 kg.
So, 50*28% = 14 kg.
So, 50*28% = 14 kg.
(9)
Naren said:
9 years ago
Please explain correctly, whether 30 is correct or 14 is correct?
If any then explain how.
If any then explain how.
Abhi said:
10 years ago
Its wrong answer is 30 kg.
How can we take water for aggregate if nothing is mentioned?
How can we take water for aggregate if nothing is mentioned?
Chijioke said:
8 years ago
Determine the quantities of water needed to mix 150kg of cement used for concrete mix.
Rohit said:
7 years ago
Water=water cement ratio* cement weight.
So, W=0.6*221=133/4.45=30.
So, W=0.6*221=133/4.45=30.
Kamran said:
10 years ago
Why we take aggregate 150 kg?
3 times of cement? Explain please?
3 times of cement? Explain please?
Sengathir said:
8 years ago
What is that 1bag cement~36 liter (or) 0.036cum please explain?