26. 

To ensure constant moisture content in aggregates

[A]. area of each aggregate pile should be large
[B]. height of each aggregate pile should not exceed 1.50 m
[C]. aggregate pile should be left for 24 hours before aggregates are used
[D]. conical heaps of aggregates should be avoided to prevent moisture variation
[E]. all the above.

Answer: Option E

Explanation:

No answer description available for this question.

Devnath Pandit said: (Jan 7, 2017)  
What is aggregate pile?

Can anybody clear it? Please.

Spandan Gowda said: (Apr 24, 2017)  
AGGREGATE PILR: Dumping of AGGREGATE in a cone shape before it is used for roofing or any other works at the sites.