43.
If P, Y and Z are the weights of cement, fine aggregates and coarse aggregates respetively and W/C is the water cement ratio, the minimum quantity of water to be added to first batch, is obtained by the equation
Discussion:
7 comments Page 1 of 1.
Baloch said:
9 years ago
As a proportion of water required for ordinary concreting is 5% of F. Aggregates + 30% of cement (by weight), the correct answer seems to be [D].
Deep said:
9 years ago
Can anybody explain clearly?
Jay prakash sah said:
8 years ago
In equation, if w/c value is computed. Then how can we find the value of water?
Haresh said:
7 years ago
Please explain it in detail.
Shahzad said:
4 years ago
How this equation is derived from any analysis behind the equations? Please explain.
(1)
Hemu said:
4 years ago
I think bz for preparing the concrete quantity of water is - 30% of the weight of cement (.3) and 5-10 % of the weight of fine aggregate .
So in this question, P is cement,
Y is fine aggregate and Z is coarse aggregate.
30% of P + 10 % of Y + 1% of z = W/C of P.
.3P + .1Y + 0.01Z = W/C* P.
So in this question, P is cement,
Y is fine aggregate and Z is coarse aggregate.
30% of P + 10 % of Y + 1% of z = W/C of P.
.3P + .1Y + 0.01Z = W/C* P.
Aaloo said:
1 year ago
Please, explain the answer.