41.
For the construction of R.C.C. slabs, columns, beams, walls, etc. the grade of concrete mix used, is
1 : 3 : 6
1 : : 3
1 : 2 : 4
1 : 1 : 2
1 : 4 : 8.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
23 comments Page 1 of 3.

Aravind gottumukkala said:   1 decade ago
1:1.5:3, because is 456-2000 specifies min grade of concrete for rcc works is M20.

Hanil.K.H said:   1 decade ago
For general R.C.C works in building, proportion of concrete is 1:1.5:3.

Darshan H A said:   9 years ago
Minimum grade of concrete for RCC work is M20 and proportion is 1 : 1.5 : 3.

Karan said:   8 years ago
Minimum grade of concrete for R.C.C. work as per IS 456 is M20 which is 1:1.5:3.

Sathyadallu said:   8 years ago
Anyone explain the answer.

S. Dharmesh said:   8 years ago
Correct answer is 1:1/2:3 according to reference book by Khurmi.

Akp said:   8 years ago
Yes, 1:1.5:3 is right answer.

Minesh Rathore said:   8 years ago
As per IS code, blow than M20 (1:1. 5:3) grades not used in Rcc work.

Manjunatha R.N. said:   8 years ago
Yes, it is revised from m15 to m20, therefore ans is m20 i.e 1:1.5:3.

Sunny said:   7 years ago
Please, check m20 proportion.