4.
Wp and Wf are the weights of a cylinder containing partially compacted and fully compacted concrete. If the compaction factor
is 0.95, the workability of concrete is

Discussion:
31 comments Page 2 of 4.
Apurva said:
7 years ago
Extremely low - 0.65 - 0.68.
Very Low - 0.75.
Low - 0.83 - 0.85.
Medium - 0.90 - 0.92.
High - 0.95.
Very Low - 0.75.
Low - 0.83 - 0.85.
Medium - 0.90 - 0.92.
High - 0.95.
Amal Ranjan said:
1 decade ago
Higher compaction factor implies higher workability.
A mix with good workability compacts easily.
A mix with good workability compacts easily.
Iskhan said:
4 months ago
CF = 0.85 low workability.
CF = 0.92 medium workability.
CF = 0.95 high workability.
CF = 0.92 medium workability.
CF = 0.95 high workability.
Sushan bastola said:
9 years ago
wp = wt of partially compacted concrete and wf = wt of fully compacted concrete.
Surya said:
6 years ago
If the compaction factor value is 0.95, then the workability will be high.
(4)
Kailingtan said:
7 years ago
Why the compaction factor test more suitable for dry mixes?
Fazul ul Rahman said:
4 years ago
Please can anyone the explain given equations?
wp /Wf.
wp /Wf.
(1)
Macdonald said:
8 years ago
Thanks for all your help by explaining the solution.
Amresh said:
1 decade ago
As it goes towards 1 its work ability increases.
Afajal Afaridi said:
8 years ago
More compaction concrete then high density .95.