4.
Wp and Wf are the weights of a cylinder containing partially compacted and fully compacted concrete. If the compaction factor
is 0.95, the workability of concrete is

Discussion:
31 comments Page 1 of 4.
Sushant Ranchi said:
5 years ago
For a good workability, the compaction factor must be between (0.7 - 0.95).
Extremely low - 0.65 to 0.68.
Very low - 0.75.
Low - 0.83 to 0.85.
Medium - 0.90 to 0.92.
High - 0.95.
Extremely low - 0.65 to 0.68.
Very low - 0.75.
Low - 0.83 to 0.85.
Medium - 0.90 to 0.92.
High - 0.95.
(18)
Amaresh said:
5 years ago
Extremely low - 0.65 to 0.68.
Very low - 0.75.
Low - 0.83 to 0.85.
Medium - 0.90 to 0.92.
High - 0.95.
Very low - 0.75.
Low - 0.83 to 0.85.
Medium - 0.90 to 0.92.
High - 0.95.
(17)
CHEEPURUPALLI ANANDA KUMAR said:
2 years ago
Extremely low -> 0.65 to 0.68.
Very low -> 0.75.
Low -> 0.83 to 0.85.
Medium -> 0.90 to 0.92.
High -> 0.95.
Very low -> 0.75.
Low -> 0.83 to 0.85.
Medium -> 0.90 to 0.92.
High -> 0.95.
(11)
Surya said:
6 years ago
If the compaction factor value is 0.95, then the workability will be high.
(4)
Ghassan Kharouf said:
1 decade ago
More compaction, means more dense material, otherwise (lower workability).
For a good workability, compaction factor must be between (0.7 - 0.95).
For a good workability, compaction factor must be between (0.7 - 0.95).
(1)
Uday Shankar said:
2 years ago
How? can anyone explain?
(1)
Kamlesh yadav said:
3 years ago
Please can anyone explain the given equations?
(1)
Fazul ul Rahman said:
4 years ago
Please can anyone the explain given equations?
wp /Wf.
wp /Wf.
(1)
Pulak moral said:
6 years ago
0.83, 0.92, 0.95 low medium and high respectively for very low 0.83>0.75 and extremely low 0.75>.
(1)
Macdonald said:
8 years ago
Thanks for all your help by explaining the solution.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers