29.
Higher workability of concrete is required if the structure is
Discussion:
14 comments Page 1 of 2.
Ahmad khalil pakistan said:
6 years ago
Option C is correct because it is not properly possible to do compaction of harsh concrete in thin and heavily reinforced section.
(3)
Bijender Singh Rana said:
8 years ago
Yes, D answer is correct, because if I can use vibration needle easily, then workability will be increased.
(1)
Vidya said:
7 years ago
High workable concrete is used in thin and heavily Reinforced structures. Less workable is used in mass concreting. The primary reason for less workable concrete in mass concreting is to avoid thermal stress developed due to the large volume of the heat of hydration. So, OPTION C is correct.
(1)
PIYUSH SINGH said:
1 decade ago
High workability is required when the structural member is thin and heavily reinforced.
Gaurav javare said:
10 years ago
Why not option C?
DEEPAK said:
9 years ago
I think option C is the correct answers.
Harrry said:
9 years ago
I too think it is option C.
Avance said:
9 years ago
@All.
It's D only. The given answer is correct.
It's D only. The given answer is correct.
Ranjit said:
9 years ago
Yeah, D is the correct answer. Because in thin structure there may compaction is done by inserting the compaction needle from the surface but which can't be done in the case of the very thick structure.
Shanky said:
8 years ago
Yes, the correct answer is 'C'. I agree.