Civil Engineering - Concrete Technology - Discussion

Discussion Forum : Concrete Technology - Section 3 (Q.No. 36)
36.
Pick up the incorrect statemnt from the following. For performing compressive strength test of cement
cement and standard sand mortar are used in the ratio of 1 : 3
water is added at the rate of + 3.0 percentage of water where P is the percentage of water for standard consistency
A cube mould of 10 cm x 10 cm x 10 cm is used
The perpared moulds are kept in a atmosphere of 90% relative humidity
The temperature of water in the submerged tank for curing moulds, should be 27° ± 2°C.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
36 comments Page 2 of 4.

Sangam said:   7 years ago
This test is done for concrete not for cement. So, The given answer A is the right one.

BUDH MAURYA said:   6 years ago
Option C & D is the right answer.

Cube size 70.6*70.6 mm2

Humidity 90%.
(1)

Hameed said:   7 years ago
The question is related for cement and not for concrete so answer A is correct.

Nizam Ali said:   3 years ago
Actually, option "A "is correct because here mentioned cement and sand mortar.
(2)

Anilpoojar said:   8 years ago
7.06 * 7.06 * 7.06cm for consistency test.

10 * 10 * 10 for strength test.

Dibya said:   8 years ago
I also agree C and D.

But how the answer A is correct? Anybody explain.

Apurba said:   1 decade ago
Cube mould size is 70.6mm*70.6mm*70.6mm. So option C is correct.

Shubham Umak said:   8 years ago
Yes, option C and D is incorrect. I too agree @Bishal.

Bishal said:   9 years ago
I too think the Option C and D is incorrect.

Soumya choudhuru said:   1 decade ago
But as per code it is 100% for 24+/-.5hrs.


Post your comments here: