Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 2 (Q.No. 38)
38.
For an ordinary Portland cement
Discussion:
26 comments Page 1 of 3.
Imran Ali magsi said:
1 year ago
Option E is correct.
As for rapid hardening residuals are 5%.
So, All options are correct.
As for rapid hardening residuals are 5%.
So, All options are correct.
WASEEM SANGI said:
3 years ago
All the given options are right so, E is the right option.
Micky said:
3 years ago
Option C is correct because option A is for rapid hardening cement.
Prasanna Gosavi said:
4 years ago
Yes, here the right answer is option E i.e. all of the above.
Prasanna Gosavi said:
4 years ago
Yes, here the right answer is option E i.e. all of the above.
Raj said:
4 years ago
Answer is D.
For 3 days=160 and for 7 days=210.
For 3 days=160 and for 7 days=210.
Pallab said:
6 years ago
It would be option (E). I too agree
Subu said:
6 years ago
Those who agree with option E, they also agree that option C is correct for OPC, but those who are saying option C is correct they are not defining why option E is incorrect. As A, B, C, D all are the necessary criteria for OPC.
PARTHA said:
6 years ago
According to MS Shetty, initial is not less than 30 and final not more than 10h.
Hardik chauhan said:
7 years ago
I agree with option C, as it says that "initial setting time is not less than 30minutes" that means it should be more than 30mnts, not less than 30. But we all know the Initial setting time of OPC is exactly 30 minutes, not more not less.