Civil Engineering - Building Construction - Discussion
Discussion Forum : Building Construction - Section 1 (Q.No. 28)
28.
In case of multi-storeyed buildings, the forms to be removed first are
Discussion:
11 comments Page 1 of 2.
Santhosh said:
6 years ago
Both a & b correct.
Because de shuttering time is the same for both.
Because de shuttering time is the same for both.
(1)
Anoop said:
10 years ago
Form means shape and structure of the object.
Selvaa said:
10 years ago
First we need to remove column in 3 - 4 days.
Vaibhav said:
10 years ago
Beam side can be removed immediately after 16 hours.
Darshan h a said:
9 years ago
First, we remove column form work within one or two days. That's why the answer should be A.
Mayur dudhatra said:
9 years ago
1st of all we need to remove column forms after only one day.
Kunal said:
8 years ago
Sides of beam or slab can be removed after 16 hours.
Vishnupriya ES said:
6 years ago
I think Column forms can also be remove after 16 hours.
Vishnupriya ES said:
6 years ago
In practical, column forms are removed first after one day.
Sudhakar padmashali said:
6 years ago
First of all, we have to remove beams because before columns we have to remove plinth beam side forms And inner side girders.
Post your comments here: