Discussion Forum : Building Construction - Section 1 (Q.No. 47)
47.
The form work from the underside of slabs, can be removed only after
Discussion:
11 comments Page 1 of 2.
Zahid said:
1 decade ago
7 days for length upto 3.5m and 14 days for length more than 3.5m.
Murugan said:
1 decade ago
We have to check the clear span length ?
Zeeshan said:
10 years ago
Why not 14 days?
(1)
Santanu tripathy said:
9 years ago
There are no mention clear span so we take 7 days.
Muhammed D. Rasheed said:
9 years ago
Its depend on a length of span with the a notice of tempreture?
Naufal Haniffa said:
9 years ago
Generally after 21-28 days that it reaches the 100% strength; otherwise based strength test report.
Roy said:
8 years ago
With props or without props?
Because without props it is 3 days. And with props, if span up to 4.5 m it is 7 days and greater than 4.5 m it is 14 days.
Because without props it is 3 days. And with props, if span up to 4.5 m it is 7 days and greater than 4.5 m it is 14 days.
Sunil thorat said:
7 years ago
Depend on slab span - 7, 14, 21 days.
Please refer IS code.
Please refer IS code.
Sagar Bahule said:
7 years ago
It depends upon the span length of the slab as the span of the slab is,
1) Less than the 5 m =07 days of curing.
2) Exceeding 5 m=14 days of curing.
1) Less than the 5 m =07 days of curing.
2) Exceeding 5 m=14 days of curing.
Muhammad Farhan Malik said:
5 years ago
For 4.5m 7 days and for more than 4.5m 14 days.
(2)