Discussion Forum : Building Construction - Section 1 (Q.No. 47)
47.
The form work from the underside of slabs, can be removed only after
Discussion:
11 comments Page 2 of 2.
Sneha Mathai said:
4 years ago
As per IS 456: 2000 clause 11.3,
* The formwork from the underside/soffit of the slab is removed after 3 days.
* For slabs spanning up to 4.5 m, their props can be removed after 7 days.
* For slabs spanning over 4.5 m, their props can be removed after 14 days.
So, the answer should be 3 days.
* The formwork from the underside/soffit of the slab is removed after 3 days.
* For slabs spanning up to 4.5 m, their props can be removed after 7 days.
* For slabs spanning over 4.5 m, their props can be removed after 14 days.
So, the answer should be 3 days.