37.
The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed
5 m
10 m
15 m
20 m
25 m.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
4 comments Page 1 of 1.

Rahul said:   8 years ago
For single stage is 5m for multi stage up to 15m and different elevation.

Chintu said:   8 years ago
Actually, 4.5 for single stage and 15 m for multistage. After 15m well point system cannot be used.
(1)

Lesner said:   9 years ago
What is single stage well point system?
(2)

Shahzaman said:   1 decade ago
The single stage well point system of dewatering and excavation can be used if the depth of excavation does not exceed.