35. 

The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about __________ mm of water column per metre height of packing.

[A]. 1-5
[B]. 20-40
[C]. 100-150
[D]. 1000-1500

Answer: Option B