Discussion Forum : Time and Work - General Questions (Q.No. 9)
9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Answer: Option
Explanation:
Whole work is done by A in | ![]() |
20 x | 5 | ![]() |
= 25 days. |
4 |
Now, | ![]() |
1 - | 4 | ![]() |
i.e., | 1 | work is done by A and B in 3 days. |
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
![]() |
![]() |
1 | - | 1 | ![]() |
= | 4 | = | 2 | . |
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. |
2 | 2 |
Discussion:
164 comments Page 11 of 17.
Inna said:
10 years ago
A's work 80% --- 20.
100% --- 25 (A).
A + B work (the remaining work means) 20% --- 3.
100% --- 15 (A+B).
(A+B) - A = B.
= 25*15/10 = 75/2 = 37*1/2.
100% --- 25 (A).
A + B work (the remaining work means) 20% --- 3.
100% --- 15 (A+B).
(A+B) - A = B.
= 25*15/10 = 75/2 = 37*1/2.
Punitsw said:
10 years ago
In simple words:
A completes 80% in 20 days so would 92% in 23 days.
Remaining 8% completed by B in 3 days (21 - 23rd).
Now if B completes 8% in 3 days. So will be able to complete 100% in 37.5 days (3 x 100/8).
A completes 80% in 20 days so would 92% in 23 days.
Remaining 8% completed by B in 3 days (21 - 23rd).
Now if B completes 8% in 3 days. So will be able to complete 100% in 37.5 days (3 x 100/8).
SUJALA said:
10 years ago
A is doing 80% work in 20 days.
80/100 = 20.
4/5 = 20/1 (cross multiplication).
= 25 days.
It means a can take time to complete 100% of work for 25 days.
A+B is doing 20% of work in 3 days.
= 20/100 = 3/1 (cross multiplication) = 15 days.
Now B to get complete 100% of work is?
(A+B)-A = B.
= 1/15-1/25 = 2/75 = 37*1/2.
80/100 = 20.
4/5 = 20/1 (cross multiplication).
= 25 days.
It means a can take time to complete 100% of work for 25 days.
A+B is doing 20% of work in 3 days.
= 20/100 = 3/1 (cross multiplication) = 15 days.
Now B to get complete 100% of work is?
(A+B)-A = B.
= 1/15-1/25 = 2/75 = 37*1/2.
Sivapriya said:
10 years ago
Hai guys I have one doubt. Will you please explain me. Geore do 3/5th work in 9 days. He then call paul and finish in 4 days. How long paul take to work by himself?
Atyanand said:
10 years ago
A complete 80% work in 20 days.
So A complete 100% work in 25 days.
Work done by A in 1 day = 1/25......equation (1).
A+B complete 20% work in 3 days.
So, A+B complete its 100% work in 15 days.
Work done by A+B in 1 day = 1/15.
From equation 1.
B = 1/15-1/25 = 2/75.
So A complete 100% work in 25 days.
Work done by A in 1 day = 1/25......equation (1).
A+B complete 20% work in 3 days.
So, A+B complete its 100% work in 15 days.
Work done by A+B in 1 day = 1/15.
From equation 1.
B = 1/15-1/25 = 2/75.
Kannan said:
10 years ago
I don't understand please explain.
Sonam said:
10 years ago
My method:
A's one day work = 80/100*1/20 = 1/25.
A+B together = 20/100*1/3 = 1/15.
B's one day work = (A+B)-A.
1/15-1/25 ---> now take LCM and solve.
You will get 2/75 i.e., 75/2 days.
Hope this helps you.
A's one day work = 80/100*1/20 = 1/25.
A+B together = 20/100*1/3 = 1/15.
B's one day work = (A+B)-A.
1/15-1/25 ---> now take LCM and solve.
You will get 2/75 i.e., 75/2 days.
Hope this helps you.
Aravind said:
10 years ago
For A 80% of work = 20 days.
100% of work = x?
Cross multiple:
x = 20*100/80.
x =25 days.
A 1 days work = 1/25....(1).
For a and b together 20% of work = 3 days.
100% of work = x?
Cross multiple x = 15 days.
A 1 day work + b 1 day work = 1/15.
1/25+ b 1 day work = 1/15.
B 1 day work = 1/15-1/25 = 2/75.
B Can complete in 75/2 = 37 1/2.
100% of work = x?
Cross multiple:
x = 20*100/80.
x =25 days.
A 1 days work = 1/25....(1).
For a and b together 20% of work = 3 days.
100% of work = x?
Cross multiple x = 15 days.
A 1 day work + b 1 day work = 1/15.
1/25+ b 1 day work = 1/15.
B 1 day work = 1/15-1/25 = 2/75.
B Can complete in 75/2 = 37 1/2.
Gaurav gupta said:
1 decade ago
Here is the solution to get total work days of A.
80% work can done in 20 days.
So 1% can be done in (20/80%) = (20/80)*100 = 25 days.
80% work can done in 20 days.
So 1% can be done in (20/80%) = (20/80)*100 = 25 days.
Srini said:
1 decade ago
A's 20% work in 5 days and A+B'in 3 days,
So B's 20 work in (1/3 - 1/5) = 2/15 i.e 15/2.
So B's 100% work in (15/2)*5 = 75/2 = 37.5 days.
So B's 20 work in (1/3 - 1/5) = 2/15 i.e 15/2.
So B's 100% work in (15/2)*5 = 75/2 = 37.5 days.
Post your comments here: