9.
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
168 comments Page 10 of 17.

VIKRAM SIHAG said:   1 decade ago
Efficeny of A+B = 20/3 = 6.66.
EFFICENCY OF A = 80/20 = 4.00.

THEN EFFICENCY OF B = 6.66-4.00 = 2.66.

DAYS TAKEN BY B = 100/2.66 = 37.5.

Gaurav gupta said:   1 decade ago
Here is the solution to get total work days of A.

80% work can done in 20 days.

So 1% can be done in (20/80%) = (20/80)*100 = 25 days.

Milan said:   5 years ago
Here;
20 is 80 %,
25 is 100%,
A+B = 3 days this is 20 %.
20% * 5 = 3 * 5 for 100% work,
B= A+B- A.
B=1/15- 1/25,
B = 2/ 75 = 37.5.

Satish said:   10 years ago
A - 20 - 80/100.
A - 1 - 80/(100 * 20) = 1/25.

A and B - 3 days = 20/100.
" 1 " = 20/(100 * 3).
= 1/15.
So,
1/15 -1/25 = 75/2.

SHIMEGHA.T.C said:   9 years ago
3(A+B)20%. = 80%(20A),
3/20*100. = 20/80*100A
15days(a+b). = 25 days A alone
B alone work = 1/25-1/15 = 2/75; 75/2.

Ram@Sravs said:   1 decade ago
Hi. @Supreeth:

In St-4:

Why had you reversed the 2/25 part to 25/2 and multiplied with 3?

Can you Explain please.

Juanita said:   1 decade ago
My understanding is that A alone does 80% work which is 5/4. Remaining 20% work is done by A & B which is 1/5.

Abhik said:   8 years ago
A 80% done in 20 days 100% done in 25 days.
Another A+B done 20%in 3 days 100% in 15 days.
Now B = 25*15/10=37.5.

Snehagoud said:   2 decades ago
A did only 80% of work out of total work in 20 days so
work done by A=80/100=5/4
so total workdone by A=20*5/4

Srujan said:   1 decade ago
Am getting troubled like this questions, can any one knows the tricks to solve these kind of problems.