A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
23 days
37 days
371/2
40 days
Answer: Option
Explanation:

Whole work is done by A in ( 20 x 5 ) = 25 days.
4

Now, ( 1 - 4 ) i.e., 1 work is done by A and B in 3 days.
5 5

Whole work will be done by A and B in (3 x 5) = 15 days.

A's 1 day's work = 1 , (A + B)'s 1 day's work = 1 .
25 15

Therefore B's 1 day's work = ( 1 - 1 ) = 4 = 2 .
15 25 150 75

So, B alone would do the work in 75 = 37 1 days.
2 2

Discussion:
168 comments Page 11 of 17.

Saiteja said:   9 years ago
20 days-80% => 1 day-4%.

In 3 days a+b-20% => 3b=20-3*4% = 8%.

b = 8/3% => 100*8/3 = 37.5.

Vijay said:   7 years ago
1day work of A : (1/20)*80/100 = 1/25,
A+B = 3/25 + 3/x=1/5(for 3days).
Find x = 37.5.

Balaji said:   1 decade ago
I can't understand the simple step anyone friends tell me (1/15-1/25) please tell me?

Swapraj said:   9 years ago
80%= 4/5.

But, work done by A = 5/4 * 20 why not 4/5 * 20.

Please explain me.

Mathi said:   2 decades ago
A = (1/20) * (80/100) = 1/25
1/A + 1/B =1/3(20/100)
1/B=(1/15) - (1/25) =2/75
(1)

Selva said:   8 months ago
a = 1/25.
a + b = 1/15.
b = 1/25 - 1/15 = 2/75 = 1/37.5(37.5 days).
(7)

Charu said:   1 decade ago
Thanks Bhasker, Ganesh and Mini... Keep up the good work!!! cheers

Kriti said:   1 decade ago
Hey guys 80/100 = 4/5 then why you people multiplying 5/4 * 20?

Prathap said:   1 decade ago
Bhaskar and rajendra you both are explained very well. Thanks.

Jiya said:   10 years ago
Still, I'm not getting why its 5/4*20? Please explain briefly.


Post your comments here:

Your comments will be displayed after verification.