Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 13)
13.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
40
50
54
60
Answer: Option
Explanation:

(A + B)'s 20 day's work = ( 1 x 20 ) = 2 .
30 3

Remaining work = ( 1 - 2 ) = 1 .
3 3

Now, 1 work is done by A in 20 days.
3

Therefore, the whole work will be done by A in (20 x 3) = 60 days.

Discussion:
63 comments Page 6 of 7.

Rohit said:   8 years ago
In how many days B will complete the same work?

Kulbhushan said:   1 decade ago
Hi, how we calculated that 1/3 work in 20 days?

Arun said:   3 years ago
Why the reaming work is -1? Explain it please.
(1)

Raj said:   1 decade ago
In how many days B alone can finish the work?

Harsimran kaur said:   7 years ago
@Pankaj.

Total time taken by B is 60 days.

Pankaj khatikkar said:   5 years ago
Can anyone explain this with LCM method?

Sinchana Shettar said:   5 years ago
Please, Explain this with LCM method.

Poorvi said:   8 years ago
Good explanations. Thank you all.

Himanshu said:   5 years ago
Nice. Thanks all for explaining.

Deepak yadav said:   1 decade ago
Please give its short trick.