Discussion Forum : Time and Work - General Questions (Q.No. 10)
10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
Answer: Option
Explanation:
(P + Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | + | 1 | ![]() |
= | 37 | . |
8 | 10 | 12 | 120 |
Work done by P, Q and R in 2 hours = | ![]() |
37 | x 2 | ![]() |
= | 37 | . |
120 | 60 |
Remaining work = | ![]() |
1 - | 37 | ![]() |
= | 23 | . |
60 | 60 |
(Q + R)'s 1 hour's work = | ![]() |
1 | + | 1 | ![]() |
= | 11 | . |
10 | 12 | 60 |
Now, | 11 | work is done by Q and R in 1 hour. |
60 |
So, | 23 | work will be done by Q and R in | ![]() |
60 | x | 23 | ![]() |
= | 23 | hours ![]() |
60 | 11 | 60 | 11 |
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
Discussion:
95 comments Page 8 of 10.
Tanuj Upadhyay said:
5 years ago
Work from 9 AM to 11 AM,
=> P+Q+R = (1/8+1/10+1/12) * 2.
=> P+Q+R = 37/60.
After 11 AM only Q & R works, So
=> Q+R = 1/10+1/12.
=> Q+R = 11/60 , this is 1 hour work.
As we know if the total work is done it will be 1.
Now predict the hours,
(37/60)+(11/60)+(11/60) => approx 1.
(2) + (1) + (1) => 4 hours.
From (9+4) AM ->> 1 PM.
=> P+Q+R = (1/8+1/10+1/12) * 2.
=> P+Q+R = 37/60.
After 11 AM only Q & R works, So
=> Q+R = 1/10+1/12.
=> Q+R = 11/60 , this is 1 hour work.
As we know if the total work is done it will be 1.
Now predict the hours,
(37/60)+(11/60)+(11/60) => approx 1.
(2) + (1) + (1) => 4 hours.
From (9+4) AM ->> 1 PM.
(1)
Gayathri said:
5 years ago
Total work needs to be completed = lcm (8,10,12) = 120 work.
Efficiency of P (work completed in 1 hr) = 120/8=15 work.
Similarly for Q=12 work and for R = 10.
Total work done by all the three in 1 hr =15+12+10 =37.
From 9 to 11 am all worked together ie. 37*2 =75 work completed out of 120.
Remaining work =120-75 = 45.
Work completed by Q and R in 1 hr = 10+12 =22.
Time taken to complete 45 work ==> 45/22 ~ 2 hrs.
ie.11 AM + 2 hrs ==> Around 1 PM work will be finished.
Efficiency of P (work completed in 1 hr) = 120/8=15 work.
Similarly for Q=12 work and for R = 10.
Total work done by all the three in 1 hr =15+12+10 =37.
From 9 to 11 am all worked together ie. 37*2 =75 work completed out of 120.
Remaining work =120-75 = 45.
Work completed by Q and R in 1 hr = 10+12 =22.
Time taken to complete 45 work ==> 45/22 ~ 2 hrs.
ie.11 AM + 2 hrs ==> Around 1 PM work will be finished.
Vishal R said:
5 years ago
I think we can do like this!
We need to find (Q+R) Work ! Since, We can write it as,
(Q+R ) = (P+Q+R ) - P ---> 1.
Therefore , P+Q+R = (1/8)+(1/10)+(1/12) = 37/120.
All of them Printed for 2 hrs, So (37/160) * 2 = 37/60.
Now find the Individual Work done by P,
P= (1/8), for 2 hrs (1/8)*2 = 1/4.
1--> (Q+R) = (37/60) - (1/4) = 11/30.
Therefore Taking, 30/11 = (approximately 2 hrs).
11 hrs + 2 hrs = 1 PM.
I hope this will be Easy to Understand!
We need to find (Q+R) Work ! Since, We can write it as,
(Q+R ) = (P+Q+R ) - P ---> 1.
Therefore , P+Q+R = (1/8)+(1/10)+(1/12) = 37/120.
All of them Printed for 2 hrs, So (37/160) * 2 = 37/60.
Now find the Individual Work done by P,
P= (1/8), for 2 hrs (1/8)*2 = 1/4.
1--> (Q+R) = (37/60) - (1/4) = 11/30.
Therefore Taking, 30/11 = (approximately 2 hrs).
11 hrs + 2 hrs = 1 PM.
I hope this will be Easy to Understand!
Parkavi said:
5 years ago
@All.
The solution is;
P Q R together work for 2 hrs
P + Q + R = 37 *2 = 74,
120-74 = 46.
Remaining 46 works done by Q and R so;
46/22.
23/11 ------ 2 1/11 hours approximately 2 hours.
So, from 11 Am +2 hrs = 1 Pm.
The solution is;
P Q R together work for 2 hrs
P + Q + R = 37 *2 = 74,
120-74 = 46.
Remaining 46 works done by Q and R so;
46/22.
23/11 ------ 2 1/11 hours approximately 2 hours.
So, from 11 Am +2 hrs = 1 Pm.
Janie said:
5 years ago
The solution is;
10 - 8=2
12 - 10=2
So, two is a common difference.
Then, P is closed at 11:AM.
11:00 + 00:30 = 11:30.
Continued for four good times then you'll get 1:00PM.
10 - 8=2
12 - 10=2
So, two is a common difference.
Then, P is closed at 11:AM.
11:00 + 00:30 = 11:30.
Continued for four good times then you'll get 1:00PM.
Parthiban said:
5 years ago
8,10,12 for this lcm 120
Assume 120 books print
Machines printing per hour
P 120/8 = 15
Q 120/10=12
R 120/12=10.
Per hour 3 machine together print books 37
Start 9 am 11 pm machine p stop the work.
2 hours all machine worked so 2 *37=74.
120-74=46 machine Q R together print in one hour 10+12=22.
So 46/22 =2.02 so 2 hours required to print remains books
After 11 am need 2 hours need so answer 1 pm.
Assume 120 books print
Machines printing per hour
P 120/8 = 15
Q 120/10=12
R 120/12=10.
Per hour 3 machine together print books 37
Start 9 am 11 pm machine p stop the work.
2 hours all machine worked so 2 *37=74.
120-74=46 machine Q R together print in one hour 10+12=22.
So 46/22 =2.02 so 2 hours required to print remains books
After 11 am need 2 hours need so answer 1 pm.
(2)
Joel said:
4 years ago
Take lcm of 8, 10'12.
Lcm = 120 units book to be printed.
P = 120/8 = 15 units/ hour.
Q = 120/10 = 12 units per hour.
R = 120/12 = 10 units per hour.
Total units per hour=15+12+10=37 units per hour.
P+q+r work together for two hour=37*2=74 units for two hours.
Remaining work=120-72=46 units.
P and R one hour efficiency=12+10=22 units per hour.
They need how much time to finish 46 units?
46/22 = 2.09 hours.
After 11 am they need 2 hours means 1 pm approximately.
Lcm = 120 units book to be printed.
P = 120/8 = 15 units/ hour.
Q = 120/10 = 12 units per hour.
R = 120/12 = 10 units per hour.
Total units per hour=15+12+10=37 units per hour.
P+q+r work together for two hour=37*2=74 units for two hours.
Remaining work=120-72=46 units.
P and R one hour efficiency=12+10=22 units per hour.
They need how much time to finish 46 units?
46/22 = 2.09 hours.
After 11 am they need 2 hours means 1 pm approximately.
(8)
Baji said:
4 years ago
This problem is simple;
First, see the difference between the machine completed work it's approximately 2 hours in each machine.
So, p machine end it's work is 11 am so,
The difference is 2.
So simply add that 11+2= 1 pm.
First, see the difference between the machine completed work it's approximately 2 hours in each machine.
So, p machine end it's work is 11 am so,
The difference is 2.
So simply add that 11+2= 1 pm.
(13)
Nav Raj Bhatta said:
4 years ago
Here,
P take a time to complete the work = 8 hours.
Q take the time to complete the work =10 hours,
R take the time to complete the work=12 hours,
One hour work by PQR=15+10+12 = 37.
Now LCM =120(total unit to complete) (120 unit means 100000).
Now time taken to complete 120 unit = 37*2 (9-11)+22 (11-12)+22(12-13)=120 unit completed till 1 AM.
P take a time to complete the work = 8 hours.
Q take the time to complete the work =10 hours,
R take the time to complete the work=12 hours,
One hour work by PQR=15+10+12 = 37.
Now LCM =120(total unit to complete) (120 unit means 100000).
Now time taken to complete 120 unit = 37*2 (9-11)+22 (11-12)+22(12-13)=120 unit completed till 1 AM.
Sai Vinitha said:
3 years ago
P - 8 d
Q - 10 d
R - 12 d -------now,LCM of p,q,r is 120.
So, P's one day hour work = 15.
Q's =12
R's. =10.
P works for 2 hours.
So, 2*15=30.
120-30=90.
Remaining work is done by Q and R = 90/22 = 4(approx).
9:00 AM + 4 hrs = 1:00 PM.
Q - 10 d
R - 12 d -------now,LCM of p,q,r is 120.
So, P's one day hour work = 15.
Q's =12
R's. =10.
P works for 2 hours.
So, 2*15=30.
120-30=90.
Remaining work is done by Q and R = 90/22 = 4(approx).
9:00 AM + 4 hrs = 1:00 PM.
(37)
Post your comments here: