Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 10)
10.
A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
11:30 A.M.
12 noon
12:30 P.M.
1:00 P.M.
Answer: Option
Explanation:

(P + Q + R)'s 1 hour's work = ( 1 + 1 + 1 ) = 37 .
8 10 12 120

Work done by P, Q and R in 2 hours = ( 37 x 2 ) = 37 .
120 60

Remaining work = ( 1 - 37 ) = 23 .
60 60

(Q + R)'s 1 hour's work = ( 1 + 1 ) = 11 .
10 12 60

Now, 11 work is done by Q and R in 1 hour.
60

So, 23 work will be done by Q and R in ( 60 x 23 ) = 23 hours = 2 hours.
60 11 60 11

So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.

Discussion:
95 comments Page 2 of 10.

Manju said:   1 decade ago
Thanks naveen sir.

Piyus said:   1 decade ago
Friends

P's 2 hr work = 1/8*2=1/4
rest 3/4 work done by q&r
q+r 1hr = 1/10 + 1/12=11/60 work
3/4 work by q&r=60/11 * 3/4=4.09

The work complete time was 9a.m+4=1p.m

Ramkumar said:   1 decade ago
Can anyone tell

Why you put last step as 9am+4?

Already p, q, r done by 2hrs and (q&r) in 4 hrs know.

Then 2+4=6 only know.

On this step I am in confusion. Help me.

Rahul said:   1 decade ago
All the machines are started at once.
we have got the solution as 4 hrs for both machines q & r
they have started at 9 a.m.
q & r work for 4 hrs

So 9+4=13 i.e,1 p.m.

Shekar said:   1 decade ago
2(1/8+1/10+1/12)+x(1/10+1/12)=1 we get x value is 2.09. required value is 11am+209=1.09pm,we taken approx value 1pm.

Parveen said:   1 decade ago
Printing Pages in one hour:
P---->12500
Q---->10000
R---->8333
Because p will be closed at 11 A.M so printed pages by P till 11 A.M (12500*2)= 25000
Remaining pages(100000-25000)= 75000
So time taken will be 75000/(10000+8333)= 4 hours(approx.)
9 A.M+ 4 hours= 1.00P.M

Sneha said:   1 decade ago
Can you please explain how 1/8+1/10+1/12= 37/120.

Ajay said:   1 decade ago
Hi I have 1 short cut to this type of problem.

a,b,c have 2hrs time diffrnce,a completed the work at 11am similarly b at 13 and c at 15. So avg of 11, 13, 15 is 13 i.e., 1.00 pm.

Alok rai said:   1 decade ago
By using concept of percentage
A's 1 day work=100/8%=12.5%
B's 1 day work=100/10%=10%
C's 1 day work=100/12%=8.5%
(A+B+C)'s 1 day work=12.5+10+8.5=31%
(A+B+C)'s 2 day work=31%*2=62%
remaining work =100%-62%=38%
(B+C)'s 1 day work=10.5%+8.5=19%
Therefore
time taken by A and B to complete the remaining work=38/19=2 hr
hence work finished at 1 pm.

Kumar said:   1 decade ago
@sneha Its just taking Lcm for 1/8+1/10+1/12 you il get 37/120.

Lcm for 8, 10, 12 is 120.

8 goes 15 times in 120 and 10 goes 12 times in 120 and 12 goes 10 times in 120.

By adding 15+10+12=37 you will get.

Hope you got it.