Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 22)
22.
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
8 days
10 days
12 days
15 days
Answer: Option
Explanation:

(A + B)'s 1 day's work = ( 1 + 1 ) = 1 .
15 10 6

Work done by A and B in 2 days = ( 1 x 2 ) = 1 .
6 3

Remaining work = ( 1 - 1 ) = 2 .
3 3

Now, 1 work is done by A in 1 day.
15

Therefore 2 work will be done by a in ( 15 x 2 ) = 10 days.
3 3

Hence, the total time taken = (10 + 2) = 12 days.

Discussion:
40 comments Page 4 of 4.

Akil Prakash said:   7 years ago
Thank you for the answer @Mr.Aj.

Sona said:   1 decade ago
Why 2 is to be added at the end?

Swathi said:   10 years ago
29x/25-x = 40 find out x value.

Bharathi said:   8 years ago
The work done 6 * 2 = 12 days.

Vivek said:   1 decade ago
2 days already completed so.

Ranjith said:   1 decade ago
A=100/15=6.66%
B=100/10=10%

Sunny said:   9 years ago
@Chinna.

How 1/6 comes?

Rahul jha said:   1 decade ago
Why we add 10+2 days?

Divya said:   9 years ago
How 1/6 came?

Kapil said:   1 decade ago
How 2/3 came?