Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 1)
1.
A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

1
4

1
10

7
15

8
15

Answer: Option
Explanation:

A's 1 day's work = 1 ;
15

B's 1 day's work = 1 ;
20

(A + B)'s 1 day's work = ( 1 + 1 ) = 7 .
15 20 60

(A + B)'s 4 day's work = ( 7 x 4 ) = 7 .
60 15

Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15

Discussion:
344 comments Page 33 of 35.

Sowmiya said:   1 year ago
How remaing work =1? Please explain to me.
(20)

Raghu said:   1 year ago
How 7 comes? Please explain.
(22)

Hemamalini said:   1 year ago
How remaining work =1 ? Please explain me.
(35)

Kalai said:   1 year ago
How remaining work =1? Please explain to me.
(7)

Sivagami said:   1 year ago
How 7/60 came? Please explain.
(6)

Ashim said:   1 year ago
How 7/60 came? Anyone, please explain to me.
(14)

Rakesh said:   1 year ago
1/15+1/20 LCM of this is 60.
So,
(1/15 * 60 + 1/20 * 60)/60we can simplify this you can get (4+3)/60 = 7/60.
(3)

Sugan said:   1 year ago
1 (total work) - 7/15 (together completed work in 4 days).
Lcm = 15 then (15/15 -7/15) = 8/15.
(7)

Nitika said:   1 year ago
The reason why we've subtract from 1:

1 represents the whole work or complete work total work considered as 1(or 100%)
(23)

John michael said:   1 year ago
15 + 20 = 35,
15 * 20 = 300,
35/300 = 7/60.
(34)